Bagmati Small Hydropower Project (32MW) – Consulting Services

Updated Feasibility Study Report for the upgradation of project from existing 22MW to 32MW as per Department of Electricity Development “Guidelines for Study of Hydropower Projects 2018”.

Overview

We supported the client to fulfill the requirement of preparation of feasibility report for capacity upgradation of the project as per the DoED standard.

Key Facts

  • Client: Mandu Hydropower Limited
  • Project: Bagmati Small Hydropower Project
  • Capacity: 32 MW

Scope of Work

  • Review of data, information from field surveys and investigations, analysis of the data,
  • Design and preparation of a report
  • Preparation of drawings

Quality, Safety & Documentation

  • Updated Feasibility Study Report (22MW+10MW)
  • Drawings and Cost Estimation for Upgradation
  • Hydrology Study using DHM data for discharge verification.
  • Civil, Hydromechanical, Electromechanical and Transmission Line optimization of existing
  • structures to accomodate upgradatio

Outcomes

The project achieved an DoED standard Updated Feasibility Study Report-32MW with clear document control and traceability. The project report got approval from DoED on 25 April 2025.

← Back to projects